top of page

Completed!! Stormwater Drainage Project

  • col517
  • Apr 21, 2023
  • 1 min read

Updated: Nov 4

Dear Residents,


Another successful and completed capital works project to report on.

We just completed a significant storm drainage project for the Barkers Point area which covered many streets.

We are confident this will have a major positive impact on heavy rain storms.

Please see pics below.

Christian DiMartino, our Supt. of Public Works, reports that we came in 40% under original engineering budget estimate.

This is a reflection of some of the new bidding and construction oversight processes we have introduced.

More projects to come!


That is all for now.

Mayor, Peter A. Forman



ree

ree

ree



 
 

Recent Posts

See All
Recent loss of trees on HAR

Dear Residents, The Board of Trustees knows how important the natural beauty of our community is to everyone, and we know that the recent removal of several trees may have been surprising and disappoi

 
 
BZA Hearing - November 17, 2025

BOARD OF ZONING APPEALS INC. VILLAGE OF SANDS POINT   PLEASE TAKE NOTICE THAT the Board of Zoning Appeals of the Incorporated Village of Sands Point will convene to hold a public hearing on Monday, No

 
 
Nassau County PD event in VSP Friday

Dear Residents, In order to provide clear information, I would like to inform you of an incident that took place Friday morning on the edge of the Village, about which some residents have inquired. Ea

 
 
bottom of page