Completed!! Stormwater Drainage Project

  • col517
  • Apr 21, 2023
  • 1 min read

Dear Residents,


Another successful and completed capital works project to report on.

We just completed a significant storm drainage project for the Barkers Point area which covered many streets.

We are confident this will have a major positive impact on heavy rain storms.

Please see pics below.

Christian DiMartino, our Supt. of Public Works, reports that we came in 40% under original engineering budget estimate.

This is a reflection of some of the new bidding and construction oversight processes we have introduced.

More projects to come!


That is all for now.

Mayor, Peter A. Forman








Recent Posts

See All
BZA Hearing - August 11, 2025

BOARD OF ZONING APPEALS INC. VILLAGE OF SANDS POINT   PLEASE TAKE NOTICE THAT the Board of Zoning Appeals of the Incorporated Village of...

 
 
About Village Taxes

2026 taxes are up exactly 2.0%--less than inflation The County controls individual property assessments Dear Residents, ...

 
 
bottom of page